PROJECT MANAGEMENT
Project
Iron Mountain NZ Head Office
Location
East Tamaki, Auckland
Size
12,500+ m2
Services Provided
Development monitoring
Project & design management of fit out
Challenges
- Consolidation of three sites into one
- Completed over two phases and a 30 month period
- Highly specialised and complex fire and security design and systems
- Multiple changes to Basebuild construction to suite fit out needs
- New Asia Pacific flagship site
Outcome
- Basebuild construction met fit out design requirements for warehouses and offices
- Project met stringent design and performance requirements for insurance and Customer marketing requirements
- Project delivered on time and budget and met desired levels of quality
- Final design increased operational and storage capacity increasing Customer revenue