Project
Industrial warehouse and office fire remediation


Client
W. Hamilton-Irvine C/- Auckland Property Management


Location
Neilpark Drive, East Tamaki, Auckland


Size
480 m2


Value
$1M


Services Provided
  • Building Surveying
  • Project management
  • Contract administration
  • Engineer to contract
Challenges
  • Aligning all fire damage with accurate Insurance Policy response.
  • With a substantial portion of the building destroyed by fire, careful assessment and integration of new and existing building elements was critical.
  • Temporary works and underpinning to a displaced precast panel necessitated close coordination between structural and geotechnical engineers.
  • Foundation modifications were required due to soft soil conditions discovered during column replacement, contributing to programme delays.
  • The presence of black mould in isolated areas required investigation and a considered remedial approach.
  • Council inspections and their request to enhance passive fire protection requirements stalled progress, despite a valid building consent.
  • Managing variation process during construction phase, discovery of additional damage and securing insurance approvals in a timely manner was essential to maintain construction momentum.
Outcome
  • Seamless integration between new and retained building elements was successfully achieved.
  • Despite challenges, the project was delivered to a high standard and in line with all necessary compliance requirements.
  • Regular and proactive communication with stakeholders helped minimise programme disruption.
  • The client received a fully remediated, code-compliant facility, ready for Leasing and reoccupation.

Client Testimonial

RDW played a key role in the successful delivery of the Neilpark Drive fire remediation project. As the property manager representing the client, I appreciated their clear communication, timely reporting, and collaborative approach throughout the works. The project involved significant structural remediation and compliance challenges, but RDW managed these efficiently while keeping all stakeholders aligned. Their professionalism and attention to detail ensured the project was completed to a high standard, and the building was handed back ready for occupation. I would happily recommend RDW for similar complex projects.

Joseph Baranyai
APM Commercial
Neilpark Drive